by John Prince
A Hornsea campaigner is taking his fight against plans for low-volume fracking at West Newton to the High Court today (Friday, November 27), amid concerns that work at the site could go ahead before a legal challenge has been heard.
Peter Lomas, who has campaigned against the onshore oil and gas industry for more than 13 years, is seeking permission to bring a judicial review of the Environment Agency’s decision to vary Rathlin Energy’s environmental permit.
He is also seeking an injunction to prevent the company from carrying out the proposed works before any judicial review is heard.
The hearing at the Royal Courts of Justice in London comes after Rathlin confirmed on Monday, November 23, that preparations were under way at its West Newton A wellsite near Burton Constable, six miles south of Hornsea.
The Environment Agency granted the permit variation in February, allowing a technique known as a “proppant squeeze” to be used. The operation falls outside the Government’s moratorium on high-volume shale gas fracking, but campaigners argue that lower-volume techniques carry similar environmental risks.
In April, East Riding councillors voted unanimously to oppose the proposals at West Newton and called on the Government to accelerate legislation to ban fracking.
Mr Lomas has brought his legal challenge on three grounds, relating to groundwater protection, climate change and the agency’s decision to grant the permit variation before reviewing Rathlin’s hydraulic fracture plan, which is intended to manage the risk of seismic activity.

An application for an injunction was lodged on September 23. A further request for urgent intervention was made on November 9 after Rathlin declined to halt its planned operations pending a hearing.
Mr Lomas said: “Rathlin’s constant stubbornness and unyielding attitude has left me with no choice other than to seek the judicial review against the EA and injunction against the operators.”
Community campaign group West Newton Said No! has launched a fundraiser to support the legal challenge.
Rathlin, which has yet to begin commercial production at West Newton A after 13 years of exploration and testing, said it intended to begin the planned well operations subject to the outcome of Friday’s proceedings.
Meanwhile, Friends of the Earth says the case highlights a loophole in England’s fracking moratorium and is urging ministers to amend the Energy Independence Bill to ban all forms of fracking.
Tony Bosworth, energy campaigner at Friends of the Earth, said: “Why are communities still having to fight fracking schemes when Labour promised in its manifesto to ban it for good?
“Ministers must amend the Energy Independence Bill to ban all types of fracking for fossil fuels once and for all – and free communities from the threat of fracking.”
An Environment Agency spokesperson said: “We’re aware of the hearing and we aren’t able to comment ahead of the case, as it is active legal proceedings.”